- Home
- Village Services
- Construction Projects
2023 PUBLIC WORKS IMPROVEMENT PROJECTS
2023 Depot Parking Lot Rehabilitation
The Depot Parking lot is complete and open.
2023 Meadowbrook Park Parking Lot
This project is complete.
Division and Main Improvements
The improvements have been completed and the intersection is open.
Division Street Extension (Verleen to Lexington)
This project is complete. Please note that there is a new 4-way stop at Division and Verleen.
Breunig Boulevard Connection to STH19/Main Street
The connection to STH 19 has been paved. The median is in and it is open to traffic.
Simon Crestway Extension (Water Wheel to South Village Limits)
The project is complete.
2024 PW Improvement Project - Prospect Road (Madison to Division)
The Staff is finalizing plans for the project and the open house for the project is scheduled for Thursday, December 7, 2023.
2024 PW Improvement Project - South Street (Fourth St. to Eighth St.)
The staff is finalizing plans for the project and the open house for the project is scheduled for Thursday, December 14, 2023.
LOCAL ROAD PROJECTS
300/400 Block of Patrick Avenue (Completed 2023)
Project Letter
Project overview
- Remove and replace the existing asphalt street surface
- Remove and replace the underlying street base materials (gravel)
- Replace the existing water main and service laterals within Right-of-Way
- Replace the existing sanitary sewer and service laterals within the Right-of-Way
- Update and improve storm sewer
- Replace the existing concrete curb and gutter
- Replace any existing concrete sidewalk and add sidewalk on both sides of the street
- Replace the existing driveway aprons
- Restore any disturbed lawn areas with topsoil and seed
- Update street lighting throughout the project
Schedule
This project is complete.
Contact information | ||
Aaron Jahncke | Bill Frederick | Northwestern Stone, LLC 4373 Pleasant View Rd. Middleton, WI 53562 (608) 836-1701 |
Street Resurfacing (Completed 2023)
The Project includes pulverizing/milling, grading, curb and gutter spot repairs, water valve repairs and adjustments, installation of chimney seals on sanitary manholes, manhole adjustments, sidewalk repairs and driveway apron replacement.
Schedule
Sausalito Drive - Complete
Coit Court - Complete
Eric Lane - Complete
Winston Way - Complete
Winston Circle - Complete
S. Madison Street - Complete
Traffic impacts/detours
To accommodate the construction activities, and for the safety of the workers, we ask that you please be aware of the construction equipment and workers and limit the use of the street during construction hours (7am – 7pm). The streets will remain open to vehicular travel throughout the project. However, drivers may encounter lane restrictions and possible minor delays during the construction. The Contractor will make every effort to provide access to driveways during the project and at the end of each day. Also, please be aware that travel within the construction zone will be at your own risk.
In order to provide the best possible asphalt surface, and for the safety of the workers, the street will be closed to ALL traffic during the placement of the second and FINAL layer of asphalt surface, and for a few hours after completion until the pavement has sufficiently cooled. The exact paving schedule is not known at this time, so please watch for progress updates on the Village web site, the activity of the asphalt paving crew and vehicles, and signs posted on the street closure (barricades). In order to minimize any potential damage to the new asphalt surface, we ask your cooperation to restrict your vehicular travel until the barricades are pulled back and the street is again open to traffic.
Contact information | ||
Aaron Jahncke | Bill Frederick | Payne and Dolan 6295 Lacy Road Fitchburg, WI 53593 (608) 849-8939 |
LRIP - Local Roads Improvement Program / MSID - Municipal Street Improvement Discretionary Funding |
Every two years the Village has the opportunity to apply for LRIP and MSID grant funding. These grants assist local governments in improving seriously deteriorating county highways, town roads, and city and village streets. LRIP is a reimbursement program which pays up to 50% of total eligible costs, with local governments providing the balance. To learn more about the process go to: https://wisconsindot.gov/pages/doing-bus/local-gov/astnce-pgms/highway/lrip.aspx |
REGIONAL PROJECTS
(NOT OVERSEEN BY THE VILLAGE)
WIS 113 (Knutson Drive to WIS 19), Dane County
Project location
WIS 113 (Knutson Drive to WIS 19), between Madison and Waunakee - Dane County (Click here for map)
Project overview
The Wisconsin Department of Transportation (WisDOT) is developing preliminary plans for a pavement replacement project on WIS 113. The 3.4-mile-long project is located in the City of Madison, Town of Westport, and Village of Waunakee, from the Knutson Drive intersection to the WIS 19 and WIS 113 roundabout intersection.
Proposed improvements:
- Replacing the WIS 113 pavement and underlying aggregate layers
- Surface repairs on the WIS 113 northbound bridge over the Yahara River
- Replacing beam guard at the WIS 113 northbound and southbound bridges over the Yahara River
- Upgrading the pedestrian crossing at the County M intersection and extending the path to Catfish Court
- Reconfiguring the left turn lanes and installing new traffic signals at the River Road intersection
- Reconstructing the Arboretum Drive/Bong Road intersection as a single lane roundabout
Schedule
- Project updates can be found here: https://projects.511wi.gov/wis113-westpoint/
Traffic impacts/detours
Traffic on WIS 113 will be staged with lane closures from Knutson Drive to River Road. WIS 113 will be closed to through traffic from River Road to WIS 19 and a detour will be posted.
Contact information
Cody Kammerzelt, P.E.
WisDOT Project Manager
(608) 243-5995
Email
Michael Bie
WisDOT Southwest Region Communications Manager
(608) 246-7928
Email
Wisconsin Department of Transportation (WisDOT)
Southwest Region, Madison Office
2101 Wright Street
Madison, WI 53704
Phone: (608) 246-3800
Fax: (608) 246-3843
TTY: 711
Email
County Highway M - Oncken Rd to STH 113
Project Location
County Highway M between Oncken Road and State Highway 113 in Westport (Click here for map)
Project Overview
Dane County has contracted with KL Engineering to complete the environmental and design phases for improvements proposed to CTH M from Oncken Rd to STH 113 in Dane County. The existing roadway is highly congested, especially during weekday commuter travel times. Residential and commercial development is planned along and near the corridor, traffic volumes are expected to increase along with congestion and potential safety issues.
KL Engineering & the design team have investigated a range of options for improving the safety and capacity of CTH M. The selected alternative includes:
- Expansion of the roadway from the two-lane section to a four-lane section with an urban median from Oncken Road to Willow Road.
- Resurfacing of the roadway from Willow Road to STH 113.
- Improvements to intersections.
- An additional bridge over Six Mile Creek, reconstruction of the existing bridge and expansion of the existing Dorn Creek box culvert.
- An off-road, multi-use trail connecting Governor Nelson State Park to WIS 113.
- A new structure over Sixmile Creek for westbound traffic, re-decking the existing structure over Sixmile Creek for eastbound traffic and expanding the existing Dorn Creek box culvert.
The Town of Westport and Village of Waunakee are also providing input in the project design.
The project is in the Final Design phase. A Public Involvement Meeting (PIM) was held September 20, 2022 and the final PIM will be in the Spring 2023. Construction is expected to begin in the Fall of 2023 and continue through the Fall of 2024.
For more information go to:
https://highway-projects-countyofdane.hub.arcgis.com/pages/cth-m
WIS 113 Northbound Lanes (Sunset Lane to County V), Dane County
Project Location
State Highway 113 Northbound from Sunset Lane in Waunakee to County Highway V in Vienna (Click here for map)
Project overview
The project will address 3.9 miles of deteriorating pavement on WIS 113 from Sunset Lane to County Trunk Highway V in Dane County. The project will consist of removing and replacing 4 inches of asphaltic pavement. The bridge over Six Mile Creek will be replaced with a wider bridge to meet future traffic projections and bring up to current standards.
Additional improvements include:
- Replacement of select culverts
- Installation of permanent pavement markings
- Replacement of curb ramps for compliance with ADA standards
- Installation of new guardrail surrounding Six Mile Creek bridge
- Upgrade railroad crossing
Public Involvement
August 2020 - Virtual Public Involvement Meeting (PIM)
Schedule
- Summer 2024 - Construction anticipated
Traffic impacts/detours
WIS 113 will be closed to through traffic during construction.
A detour will utilize the following routes:
- Northbound WIS 113:
- WIS 19 East to Interstate 39/90/94 North to WIS 60 West
- Southbound WIS 113:
- WIS 60 East to Interstate 39/90/94 South to WIS 19 West
Status/phase
Design
Contact information
Amy Coughlin, P.E.
WisDOT Project Manager
(608) 245-5358
Email
Michael Bie
WisDOT Southwest Region Communications Manager
(608) 246-7928
Email
Wisconsin Department of Transportation (WisDOT)
Southwest Region, Madison Office
2101 Wright Street
Madison, WI 53704
Phone: (608) 246-3800
Fax: (608) 246-3843
TTY: 711
WIS 19 (Division Street to River Road), Dane County
Project Location
State Highway 19 from Division Street East to the existing River Road roundabout. (Click here for map)
Project Overview
The Wisconsin Department of Transportation (WisDOT) is developing preliminary plans for a resurfacing project on WIS 19. The 3.6-mile-long project is located in the Town of Westport and Village of Waunakee, from the Division Street intersection to River Road intersection. Exception to the project length at the WIS 113/County I roundabout, constructed in 2018.
Proposed improvements:
- Resurface existing pavement (mill and overlay)
- Construct offset left-turn lanes and traffic signal upgrades at the WIS 19 and Schumacher Road/Raemisch Road intersection
- Update curb ramps as needed to meet American with Disabilities (ADA) requirements
- Culvert pipe replacements
- Paint railing on WIS 19 bridge over Sixmile Creek
Schedule
- May 3, 2022 - Public Involvement Meeting
- April 2022 - Public Involvement Meeting
- 2026 - Construction anticipated
Traffic impacts/detours
Flagging operations during construction
Status/phase
Design
Contact information
Jennifer Kobryn, P.E.
WisDOT Project Development Supervisor
(608) 246-5339
Email
Michael Bie
WisDOT Southwest Region Communications Manager
(608) 246-7928
Email
Wisconsin Department of Transportation (WisDOT)
Southwest Region, Madison Office
2101 Wright Street
Madison, WI 53704
Phone: (608) 246-3800
Fax: (608) 246-3843
TTY: 711
Email: swr.dtsd@dot.wi.gov
ANNUAL MAINTENANCE PROJECTS
Chip Sealing
The Village will be chip sealing several streets to prolong the life of the roadways. For a map of streets, click here.
Chip Sealing is a pavement surface treatment that combines one or more layer(s) of asphalt with one or more layer(s) of fine aggregate. Chip sealing is typically used on roads carrying lower traffic volumes, and the process is often referred to as "asphaltic surface treatment".
Chip sealing consists of evenly distributing a thin base of hot bitumen or asphalt onto an existing pavement and then embedding finely graded aggregate into it. The aggregate is evenly distributed over the seal spray, then rolled into a smooth pavement surface. It can keep pavement in good condition longer by sealing out water and repairing minor cracks.
Sidewalk Repairs
In an attempt to ensure that sidewalks are reasonably safe for public travel, each year the Village engineering department administers a Sidewalk Safety Program. The Village Board has established the criteria used for determining unsafe or defective sidewalks and the Village staff inspects the public sidewalks within the Village right-of-way for defects or unsafe conditions based on the established criteria.
If your sidewalk was marked for repairs, you, as a property owner have a couple of options. First, the Village will do the repairs as part of the Sidewalk Repair Project. The Village shares the incurred cost of the Village-implemented repair with the homeowner. Property owners will be assessed 50% of the incurred costs of the repairs and these costs will be collected using the special assessment process. The proposed cost of replacements will be determined after the inspection are complete and the construction contract has been awarded. The final costs and assessments will be mailed to property owners after the work has been completed.
Alternatively, property owners may elect to complete the repairs themselves; however, the repairs will need to be completed within 20 days of the notification. Please be advised that you are strongly encouraged to hire a qualified concrete contractor (as determined by the Village), and the work must be completed in accordance with the Village Standard Specifications. Also, you or your contractor are required to first obtain a Street Opening Permit for the repairs, and if the repairs are not done properly they will be completed by the Village, and assessed to you as discussed above. Please note that property owners will NOT be reimbursed for any cost of repairs completed on your own.
We appreciate your cooperation and if you have any questions or concerns, please contact Aaron Jahncke, Village Engineer at (608) 849-6469, or by email .