Blasting Information

Blasting Notices - Updated 10/03/2022

ATTENTION
HERITAGE HILLS BLASTING PHASE 4
Tuesday, October 4, 2022 

The contractor for the Heritage Hills subdivision, at the corner of North Division Street and STH 19/113, will be blasting 1-3 times between the hours of 9-11 a.m. and 1-3 p.m. on, Tuesday, October 4, 2022 weather permitting.

There will be three air horn signals sounded one minute prior to each blast followed by one prolonged air horn signal after each blast is deemed all clear.  On average each blast duration is 500 milliseconds, equivalent to half of a second.

Ground vibration and air blast will be measured with seismographs located on the West and North side of the subdivision property.  All drilling and blasting operations will be conducted in accordance with:

  • The Village of Waunakee regulations and permit requirements
  • Bureau of Alcohol, Tobacco and Firearms – 27 CFR 181
  • MSHA 30 CFR Part 56 Safety and Health Standards 
  • MSHA 30 – Subchapter H – Education and Training
  • Wisconsin Department of Safety and Professional Services SPS 307.43 

Questions or concerns regarding the drilling and blasting process should be directed to:

Brandon Rolsma
SX Blasting
N59 W14601 Bobolink Ave
Menomonee Falls, WI  53051
(414)235-0902
brandon@sxblasting.com

ATTENTION
HERITAGE HILLS BLASTING PHASE 4
Monday, October 3, 2022 

The contractor for the Heritage Hills subdivision, at the corner of North Division Street and STH 19/113, will be blasting 1-3 times between the hours of 9-11 a.m. and 1-3 p.m. on, Monday, October 3, 2022 weather permitting.

There will be three air horn signals sounded one minute prior to each blast followed by one prolonged air horn signal after each blast is deemed all clear.  On average each blast duration is 500 milliseconds, equivalent to half of a second.

Ground vibration and air blast will be measured with seismographs located on the West and North side of the subdivision property.  All drilling and blasting operations will be conducted in accordance with:

  • The Village of Waunakee regulations and permit requirements
  • Bureau of Alcohol, Tobacco and Firearms – 27 CFR 181
  • MSHA 30 CFR Part 56 Safety and Health Standards 
  • MSHA 30 – Subchapter H – Education and Training
  • Wisconsin Department of Safety and Professional Services SPS 307.43 

Questions or concerns regarding the drilling and blasting process should be directed to:

Brandon Rolsma
SX Blasting
N59 W14601 Bobolink Ave
Menomonee Falls, WI  53051
(414)235-0902
brandon@sxblasting.com

ATTENTION
HERITAGE HILLS BLASTING PHASE 4
Friday, September 30, 2022

The contractor for the Heritage Hills subdivision, at the corner of North Division Street and STH 19/113, will be blasting 1-3 times between the hours of 9-11 a.m. and 1-3 p.m. on, Friday, September 30, 2022 weather permitting.

There will be three air horn signals sounded one minute prior to each blast followed by one prolonged air horn signal after each blast is deemed all clear.  On average each blast duration is 500 milliseconds, equivalent to half of a second.

Ground vibration and air blast will be measured with seismographs located on the West and North side of the subdivision property.  All drilling and blasting operations will be conducted in accordance with:

  • The Village of Waunakee regulations and permit requirements
  • Bureau of Alcohol, Tobacco and Firearms – 27 CFR 181
  • MSHA 30 CFR Part 56 Safety and Health Standards 
  • MSHA 30 – Subchapter H – Education and Training
  • Wisconsin Department of Safety and Professional Services SPS 307.43 

Questions or concerns regarding the drilling and blasting process should be directed to:

Brandon Rolsma
SX Blasting
N59 W14601 Bobolink Ave
Menomonee Falls, WI  53051
(414)235-0902
brandon@sxblasting.com

ATTENTION
HERITAGE HILLS BLASTING PHASE 4
Thursday, September 29, 2022 

The contractor for the Heritage Hills subdivision, at the corner of North Division Street and STH 19/113, will be blasting 2-3 times between the hours of 9-11 a.m. and 1-3 p.m. on, Thursday, September 29, 2022 weather permitting.

There will be three air horn signals sounded one minute prior to each blast followed by one prolonged air horn signal after each blast is deemed all clear.  On average each blast duration is 500 milliseconds, equivalent to half of a second.

Ground vibration and air blast will be measured with seismographs located on the West and North side of the subdivision property.  All drilling and blasting operations will be conducted in accordance with:

  • The Village of Waunakee regulations and permit requirements
  • Bureau of Alcohol, Tobacco and Firearms – 27 CFR 181
  • MSHA 30 CFR Part 56 Safety and Health Standards 
  • MSHA 30 – Subchapter H – Education and Training
  • Wisconsin Department of Safety and Professional Services SPS 307.43 

Questions or concerns regarding the drilling and blasting process should be directed to:

Brandon Rolsma
SX Blasting
N59 W14601 Bobolink Ave
Menomonee Falls, WI  53051
(414)235-0902
brandon@sxblasting.com

ATTENTION
HERITAGE HILLS BLASTING PHASE 4
Wednesday, September 28, 2022 

The contractor for the Heritage Hills subdivision, at the corner of North Division Street and STH 19/113, will be blasting 2-3 times between the hours of 9-11 a.m. and 1-3 p.m. on, Wednesday, September 28, 2022 weather permitting.

There will be three air horn signals sounded one minute prior to each blast followed by one prolonged air horn signal after each blast is deemed all clear.  On average each blast duration is 500 milliseconds, equivalent to half of a second.

Ground vibration and air blast will be measured with seismographs located on the West and North side of the subdivision property.  All drilling and blasting operations will be conducted in accordance with:

  • The Village of Waunakee regulations and permit requirements
  • Bureau of Alcohol, Tobacco and Firearms – 27 CFR 181
  • MSHA 30 CFR Part 56 Safety and Health Standards 
  • MSHA 30 – Subchapter H – Education and Training
  • Wisconsin Department of Safety and Professional Services SPS 307.43 

Questions or concerns regarding the drilling and blasting process should be directed to:

Brandon Rolsma
SX Blasting
N59 W14601 Bobolink Ave
Menomonee Falls, WI  53051
(414)235-0902
brandon@sxblasting.com

ATTENTION
HERITAGE HILLS BLASTING PHASE 4
Tuesday, September 27, 2022 

The contractor for the Heritage Hills subdivision, at the corner of North Division Street and STH 19/113, will be blasting 2-3 times between the hours of 9-11 a.m. and 1-3 p.m. on, Tuesday, September 27, 2022 weather permitting.

There will be three air horn signals sounded one minute prior to each blast followed by one prolonged air horn signal after each blast is deemed all clear.  On average each blast duration is 500 milliseconds, equivalent to half of a second.

Ground vibration and air blast will be measured with seismographs located on the West and North side of the subdivision property.  All drilling and blasting operations will be conducted in accordance with:

  • The Village of Waunakee regulations and permit requirements
  • Bureau of Alcohol, Tobacco and Firearms – 27 CFR 181
  • MSHA 30 CFR Part 56 Safety and Health Standards 
  • MSHA 30 – Subchapter H – Education and Training
  • Wisconsin Department of Safety and Professional Services SPS 307.43 

Questions or concerns regarding the drilling and blasting process should be directed to:

Brandon Rolsma
SX Blasting
N59 W14601 Bobolink Ave
Menomonee Falls, WI  53051
(414)235-0902
brandon@sxblasting.com

ATTENTION
HERITAGE HILLS BLASTING PHASE 4
Monday, September 26, 2022

The contractor for the Heritage Hills subdivision, at the corner of North Division Street and STH 19/113, will be blasting 2-3 times between the hours of 9-11 a.m. and 1-3 p.m. on, Monday, September 26, 2022 weather permitting.

There will be three air horn signals sounded one minute prior to each blast followed by one prolonged air horn signal after each blast is deemed all clear.  On average each blast duration is 500 milliseconds, equivalent to half of a second.

Ground vibration and air blast will be measured with seismographs located on the West and North side of the subdivision property.  All drilling and blasting operations will be conducted in accordance with:

  • The Village of Waunakee regulations and permit requirements
  • Bureau of Alcohol, Tobacco and Firearms – 27 CFR 181
  • MSHA 30 CFR Part 56 Safety and Health Standards 
  • MSHA 30 – Subchapter H – Education and Training
  • Wisconsin Department of Safety and Professional Services SPS 307.43 

Questions or concerns regarding the drilling and blasting process should be directed to:

Brandon Rolsma
SX Blasting
N59 W14601 Bobolink Ave
Menomonee Falls, WI  53051
(414)235-0902
brandon@sxblasting.com

ATTENTION
HERITAGE HILLS BLASTING PHASE 4
Friday, September 23, 2022

The contractor for the Heritage Hills subdivision, at the corner of North Division Street and STH 19/113, will be blasting 2-3 times between the hours of 9-11 a.m. and 1-3 p.m. on, Friday, September 23, 2022 weather permitting.

There will be three air horn signals sounded one minute prior to each blast followed by one prolonged air horn signal after each blast is deemed all clear.  On average each blast duration is 500 milliseconds, equivalent to half of a second.

Ground vibration and air blast will be measured with seismographs located on the West and North side of the subdivision property.  All drilling and blasting operations will be conducted in accordance with:

  • The Village of Waunakee regulations and permit requirements
  • Bureau of Alcohol, Tobacco and Firearms – 27 CFR 181
  • MSHA 30 CFR Part 56 Safety and Health Standards 
  • MSHA 30 – Subchapter H – Education and Training
  • Wisconsin Department of Safety and Professional Services SPS 307.43 

Questions or concerns regarding the drilling and blasting process should be directed to:

Brandon Rolsma
SX Blasting
N59 W14601 Bobolink Ave
Menomonee Falls, WI  53051
(414)235-0902
brandon@sxblasting.com

ATTENTION
HERITAGE HILLS BLASTING PHASE 4
Thursday, September 22, 2022

The contractor for the Heritage Hills subdivision, at the corner of North Division Street and STH 19/113, will be blasting 2-3 times between the hours of 9-11 a.m. and 1-3 p.m. on, Thursday, September 22, 2022 weather permitting.

There will be three air horn signals sounded one minute prior to each blast followed by one prolonged air horn signal after each blast is deemed all clear.  On average each blast duration is 500 milliseconds, equivalent to half of a second.

Ground vibration and air blast will be measured with seismographs located on the West and North side of the subdivision property.  All drilling and blasting operations will be conducted in accordance with:

  • The Village of Waunakee regulations and permit requirements
  • Bureau of Alcohol, Tobacco and Firearms – 27 CFR 181
  • MSHA 30 CFR Part 56 Safety and Health Standards 
  • MSHA 30 – Subchapter H – Education and Training
  • Wisconsin Department of Safety and Professional Services SPS 307.43 

Questions or concerns regarding the drilling and blasting process should be directed to:

Brandon Rolsma
SX Blasting
N59 W14601 Bobolink Ave
Menomonee Falls, WI  53051
(414)235-0902
brandon@sxblasting.com

ATTENTION
HERITAGE HILLS BLASTING PHASE 4
Wednesday September 21, 2022

The contractor for the Heritage Hills subdivision, at the corner of North Division Street and STH 19/113, will be blasting 2-3 times between the hours of 9-11 a.m. and 1-3 p.m. on, Wednesday, September 21, 2022 weather permitting.

There will be three air horn signals sounded one minute prior to each blast followed by one prolonged air horn signal after each blast is deemed all clear.  On average each blast duration is 500 milliseconds, equivalent to half of a second.

Ground vibration and air blast will be measured with seismographs located on the West and North side of the subdivision property.  All drilling and blasting operations will be conducted in accordance with:

  • The Village of Waunakee regulations and permit requirements
  • Bureau of Alcohol, Tobacco and Firearms – 27 CFR 181
  • MSHA 30 CFR Part 56 Safety and Health Standards 
  • MSHA 30 – Subchapter H – Education and Training
  • Wisconsin Department of Safety and Professional Services SPS 307.43 

Questions or concerns regarding the drilling and blasting process should be directed to:

Brandon Rolsma
SX Blasting
N59 W14601 Bobolink Ave
Menomonee Falls, WI  53051
(414)235-0902
brandon@sxblasting.com

ATTENTION
HERITAGE HILLS BLASTING PHASE 4
Monday, September 19, 2022

The contractor for the Heritage Hills subdivision, at the corner of North Division Street and STH 19/113, will be blasting 2-3 times between the hours of 9-11 a.m. and 1-3 p.m. on, Monday, September 19th, 2022 weather permitting.

There will be three air horn signals sounded one minute prior to each blast followed by one prolonged air horn signal after each blast is deemed all clear.  On average each blast duration is 500 milliseconds, equivalent to half of a second.

Ground vibration and air blast will be measured with seismographs located on the West and North side of the subdivision property.  All drilling and blasting operations will be conducted in accordance with:

  • The Village of Waunakee regulations and permit requirements
  • Bureau of Alcohol, Tobacco and Firearms – 27 CFR 181
  • MSHA 30 CFR Part 56 Safety and Health Standards 
  • MSHA 30 – Subchapter H – Education and Training
  • Wisconsin Department of Safety and Professional Services SPS 307.43 

Questions or concerns regarding the drilling and blasting process should be directed to:

Brandon Rolsma
SX Blasting
N59 W14601 Bobolink Ave
Menomonee Falls, WI  53051
(414)235-0902
brandon@sxblasting.com

ATTENTION
HERITAGE HILLS BLASTING PHASE 4
Friday, September 16, 2022

The contractor for the Heritage Hills subdivision, at the corner of North Division Street and STH 19/113, will be blasting 2-3 times between the hours of 9-11 a.m. and 1-3 p.m. on, Friday, September 16th, 2022 weather permitting.

There will be three air horn signals sounded one minute prior to each blast followed by one prolonged air horn signal after each blast is deemed all clear.  On average each blast duration is 500 milliseconds, equivalent to half of a second.

Ground vibration and air blast will be measured with seismographs located on the West and North side of the subdivision property.  All drilling and blasting operations will be conducted in accordance with:

  • The Village of Waunakee regulations and permit requirements
  • Bureau of Alcohol, Tobacco and Firearms – 27 CFR 181
  • MSHA 30 CFR Part 56 Safety and Health Standards 
  • MSHA 30 – Subchapter H – Education and Training
  • Wisconsin Department of Safety and Professional Services SPS 307.43 

Questions or concerns regarding the drilling and blasting process should be directed to:

Brandon Rolsma
SX Blasting
N59 W14601 Bobolink Ave
Menomonee Falls, WI  53051
(414)235-0902
brandon@sxblasting.com

ATTENTION
HERITAGE HILLS BLASTING PHASE 4
Thursday, September 15, 2022

The contractor for the Heritage Hills subdivision, at the corner of North Division Street and STH 19/113, will be blasting 2-3 times between the hours of 9-11 a.m. and 1-3 p.m. on, Thursday, September 15th, 2022 weather permitting.

There will be three air horn signals sounded one minute prior to each blast followed by one prolonged air horn signal after each blast is deemed all clear.  On average each blast duration is 500 milliseconds, equivalent to half of a second.

Ground vibration and air blast will be measured with seismographs located on the West and North side of the subdivision property.  All drilling and blasting operations will be conducted in accordance with:

  • The Village of Waunakee regulations and permit requirements
  • Bureau of Alcohol, Tobacco and Firearms – 27 CFR 181
  • MSHA 30 CFR Part 56 Safety and Health Standards 
  • MSHA 30 – Subchapter H – Education and Training
  • Wisconsin Department of Safety and Professional Services SPS 307.43 

Questions or concerns regarding the drilling and blasting process should be directed to:

Brandon Rolsma
SX Blasting
N59 W14601 Bobolink Ave
Menomonee Falls, WI  53051
(414)235-0902
brandon@sxblasting.com

ATTENTION
HERITAGE HILLS BLASTING PHASE 4
Tuesday, September 13, 2022

The contractor for the Heritage Hills subdivision, at the corner of North Division Street and STH 19/113, will be blasting 2-3 times between the hours of 9-11 a.m. and 1-3 p.m. on, Tuesday, September 13th, 2022 weather permitting.

There will be three air horn signals sounded one minute prior to each blast followed by one prolonged air horn signal after each blast is deemed all clear.  On average each blast duration is 500 milliseconds, equivalent to half of a second.

Ground vibration and air blast will be measured with seismographs located on the West and North side of the subdivision property.  All drilling and blasting operations will be conducted in accordance with:

  • The Village of Waunakee regulations and permit requirements
  • Bureau of Alcohol, Tobacco and Firearms – 27 CFR 181
  • MSHA 30 CFR Part 56 Safety and Health Standards 
  • MSHA 30 – Subchapter H – Education and Training
  • Wisconsin Department of Safety and Professional Services SPS 307.43 

Questions or concerns regarding the drilling and blasting process should be directed to:

Brandon Rolsma
SX Blasting
N59 W14601 Bobolink Ave
Menomonee Falls, WI  53051
(414)235-0902
brandon@sxblasting.com

ATTENTION
HERITAGE HILLS BLASTING PHASE 4
Thursday, September 8, 2022

The contractor for the Heritage Hills subdivision, at the corner of North Division Street and STH 19/113, will be blasting 2-3 times between the hours of 9-11 a.m. and 1-3 p.m. on, Thursday, September 8, 2022 weather permitting.

There will be three air horn signals sounded one minute prior to each blast followed by one prolonged air horn signal after each blast is deemed all clear.  On average each blast duration is 500 milliseconds, equivalent to half of a second.

Ground vibration and air blast will be measured with seismographs located on the West and North side of the subdivision property.  All drilling and blasting operations will be conducted in accordance with:

  • The Village of Waunakee regulations and permit requirements
  • Bureau of Alcohol, Tobacco and Firearms – 27 CFR 181
  • MSHA 30 CFR Part 56 Safety and Health Standards 
  • MSHA 30 – Subchapter H – Education and Training
  • Wisconsin Department of Safety and Professional Services SPS 307.43 

Questions or concerns regarding the drilling and blasting process should be directed to:

Brandon Rolsma
SX Blasting
N59 W14601 Bobolink Ave
Menomonee Falls, WI  53051
(414)235-0902
brandon@sxblasting.com

ATTENTION
HERITAGE HILLS BLASTING PHASE 4
Wednesday, September 7, 2022

The contractor for the Heritage Hills subdivision, at the corner of North Division Street and STH 19/113, will be blasting 2-3 times between the hours of 9-11 a.m. and 1-3 p.m. on, Wednesday, September 7, 2022 weather permitting.

There will be three air horn signals sounded one minute prior to each blast followed by one prolonged air horn signal after each blast is deemed all clear.  On average each blast duration is 500 milliseconds, equivalent to half of a second.

Ground vibration and air blast will be measured with seismographs located on the West and North side of the subdivision property.  All drilling and blasting operations will be conducted in accordance with:

  • The Village of Waunakee regulations and permit requirements
  • Bureau of Alcohol, Tobacco and Firearms – 27 CFR 181
  • MSHA 30 CFR Part 56 Safety and Health Standards 
  • MSHA 30 – Subchapter H – Education and Training
  • Wisconsin Department of Safety and Professional Services SPS 307.43 

Questions or concerns regarding the drilling and blasting process should be directed to:

Brandon Rolsma
SX Blasting
N59 W14601 Bobolink Ave
Menomonee Falls, WI  53051
(414)235-0902
brandon@sxblasting.com

ATTENTION
HERITAGE HILLS BLASTING PHASE 4
Tuesday, September 6, 2022

The contractor for the Heritage Hills subdivision, at the corner of North Division Street and STH 19/113, will be blasting 2-3 times between the hours of 9-11 a.m. and 1-3 p.m. on, Tuesday, September 6, 2022 weather permitting.

There will be three air horn signals sounded one minute prior to each blast followed by one prolonged air horn signal after each blast is deemed all clear.  On average each blast duration is 500 milliseconds, equivalent to half of a second.

Ground vibration and air blast will be measured with seismographs located on the West and North side of the subdivision property.  All drilling and blasting operations will be conducted in accordance with:

  • The Village of Waunakee regulations and permit requirements
  • Bureau of Alcohol, Tobacco and Firearms – 27 CFR 181
  • MSHA 30 CFR Part 56 Safety and Health Standards 
  • MSHA 30 – Subchapter H – Education and Training
  • Wisconsin Department of Safety and Professional Services SPS 307.43 

Questions or concerns regarding the drilling and blasting process should be directed to:

Brandon Rolsma
SX Blasting
N59 W14601 Bobolink Ave
Menomonee Falls, WI  53051
(414)235-0902
brandon@sxblasting.com

ATTENTION
HERITAGE HILLS BLASTING PHASE 4
Friday, September 2, 2022

The contractor for the Heritage Hills subdivision, at the corner of North Division Street and STH 19/113, will be blasting 2-3 times between the hours of 9-11 a.m. and 1-3 p.m. on, Friday, September 2, 2022 weather permitting.

There will be three air horn signals sounded one minute prior to each blast followed by one prolonged air horn signal after each blast is deemed all clear.  On average each blast duration is 500 milliseconds, equivalent to half of a second.

Ground vibration and air blast will be measured with seismographs located on the West and North side of the subdivision property.  All drilling and blasting operations will be conducted in accordance with:

  • The Village of Waunakee regulations and permit requirements
  • Bureau of Alcohol, Tobacco and Firearms – 27 CFR 181
  • MSHA 30 CFR Part 56 Safety and Health Standards 
  • MSHA 30 – Subchapter H – Education and Training
  • Wisconsin Department of Safety and Professional Services SPS 307.43 

Questions or concerns regarding the drilling and blasting process should be directed to:

Brandon Rolsma
SX Blasting
N59 W14601 Bobolink Ave
Menomonee Falls, WI  53051
(414)235-0902
brandon@sxblasting.com

ATTENTION

HERITAGE HILLS BLASTING 
PHASE 4

Thursday, September 1, 2022

The contractor for the Heritage Hills subdivision, at the corner of North Division Street and STH 19/113, will be blasting 2-3 times between the hours of 9-11 a.m. and 1-3 p.m. on, Thursday, September 1, 2022 weather permitting.

There will be three air horn signals sounded one minute prior to each blast followed by one prolonged air horn signal after each blast is deemed all clear.  On average each blast duration is 500 milliseconds, equivalent to half of a second.

Ground vibration and air blast will be measured with seismographs located on the West and North side of the subdivision property.  All drilling and blasting operations will be conducted in accordance with:

  • The Village of Waunakee regulations and permit requirements
  • Bureau of Alcohol, Tobacco and Firearms – 27 CFR 181
  • MSHA 30 CFR Part 56 Safety and Health Standards 
  • MSHA 30 – Subchapter H – Education and Training
  • Wisconsin Department of Safety and Professional Services SPS 307.43 

Questions or concerns regarding the drilling and blasting process should be directed to:

Brandon Rolsma
SX Blasting
N59 W14601 Bobolink Ave
Menomonee Falls, WI  53051
(414)235-0902
brandon@sxblasting.com

ATTENTION

HERITAGE HILLS BLASTING PHASE 4

Wednesday, August 31, 2022

The contractor for the Heritage Hills subdivision, at the corner of North Division Street and STH 19/113, will be blasting 2-3 times between the hours of 9-11 a.m. and 1-3 p.m. on , Tuesday, August 31, 2022, weather permitting.

There will be three air horn signals sounded one minute prior to each blast followed by one prolonged air horn signal after each blast is deemed all clear.  On average each blast duration is 500 milliseconds, equivalent to half of a second.

Ground vibration and air blast will be measured with seismographs located on the West and North side of the subdivision property.  All drilling and blasting operations will be conducted in accordance with:

  • The Village of Waunakee regulations and permit requirements
  • Bureau of Alcohol, Tobacco and Firearms – 27 CFR 181
  • MSHA 30 CFR Part 56 Safety and Health Standards 
  • MSHA 30 – Subchapter H – Education and Training
  • Wisconsin Department of Safety and Professional Services SPS 307.43 

Questions or concerns regarding the drilling and blasting process should be directed to:

Brandon Rolsma
SX Blasting
N59 W14601 Bobolink Ave
Menomonee Falls, WI  53051
(414)235-0902
brandon@sxblasting.com

ATTENTION

HERITAGE HILLS BLASTING PHASE 4

Tuesday, August 30, 2022

The contractor for the Heritage Hills subdivision, at the corner of North Division Street and STH 19/113, will be blasting 2-3 times between the hours of 9-11 a.m. and 1-3 p.m. on , Tuesday, August 30, 2022, weather permitting.

There will be three air horn signals sounded one minute prior to each blast followed by one prolonged air horn signal after each blast is deemed all clear.  On average each blast duration is 500 milliseconds, equivalent to half of a second.

Ground vibration and air blast will be measured with seismographs located on the West and North side of the subdivision property.  All drilling and blasting operations will be conducted in accordance with:

  • The Village of Waunakee regulations and permit requirements
  • Bureau of Alcohol, Tobacco and Firearms – 27 CFR 181
  • MSHA 30 CFR Part 56 Safety and Health Standards 
  • MSHA 30 – Subchapter H – Education and Training
  • Wisconsin Department of Safety and Professional Services SPS 307.43 

Questions or concerns regarding the drilling and blasting process should be directed to:

Brandon Rolsma
SX Blasting
N59 W14601 Bobolink Ave
Menomonee Falls, WI  53051
(414)235-0902
brandon@sxblasting.com 


ATTENTION
HERITAGE HILLS BLASTING PHASE 4
Monday, August 29, 2022

The contractor for the Heritage Hills subdivision, at the corner of North Division Street and STH 19/113, will be blasting 2-3 times between the hours of 9-11 a.m. and 1-3 p.m. on , Monday, August 29, 2022, weather permitting.

There will be three air horn signals sounded one minute prior to each blast followed by one prolonged air horn signal after each blast is deemed all clear.  On average each blast duration is 500 milliseconds, equivalent to half of a second.

Ground vibration and air blast will be measured with seismographs located on the West and North side of the subdivision property.  All drilling and blasting operations will be conducted in accordance with:

  • The Village of Waunakee regulations and permit requirements
  • Bureau of Alcohol, Tobacco and Firearms – 27 CFR 181
  • MSHA 30 CFR Part 56 Safety and Health Standards 
  • MSHA 30 – Subchapter H – Education and Training
  • Wisconsin Department of Safety and Professional Services SPS 307.43 

Questions or concerns regarding the drilling and blasting process should be directed to:

Brandon Rolsma
SX Blasting
N59 W14601 Bobolink Ave
Menomonee Falls, WI  53051
(414)235-0902
brandon@sxblasting.com 


ATTENTION

HERITAGE HILLS BLASTING PHASE 4
Friday, August 26, 2022

The contractor for the Heritage Hills subdivision, at the corner of North Division Street and STH 19/113, will be blasting 2-3 times between the hours of 9-11 a.m. and 1-3 p.m. on , Friday, August 26, 2022, weather permitting.

There will be three air horn signals sounded one minute prior to each blast followed by one prolonged air horn signal after each blast is deemed all clear.  On average each blast duration is 500 milliseconds, equivalent to half of a second.

Ground vibration and air blast will be measured with seismographs located on the West and North side of the subdivision property.  All drilling and blasting operations will be conducted in accordance with:

  • The Village of Waunakee regulations and permit requirements
  • Bureau of Alcohol, Tobacco and Firearms – 27 CFR 181
  • MSHA 30 CFR Part 56 Safety and Health Standards 
  • MSHA 30 – Subchapter H – Education and Training
  • Wisconsin Department of Safety and Professional Services SPS 307.43 

Questions or concerns regarding the drilling and blasting process should be directed to:

Brandon Rolsma

SX Blasting
N59 W14601 Bobolink Ave
Menomonee Falls, WI  53051
(414)235-0902
brandon@sxblasting.com 

ATTENTION
QUINCY RIDGE BLASTING
TOWN OF WESTPORT
Friday, September 2, 2022

The contractor for the Quincey Ridge Quarry Project, at 6355 Schumacher Road, will be blasting 2-3 times between the hours of 10 a.m. - 1 p.m. on Friday, September 2, 2022, weather permitting.

There will be three air horn signals sounded one minute prior to each blast followed by one prolonged air horn signal after each blast is deemed all clear.  On average each blast duration is 500 milliseconds, equivalent to half of a second.

Ground vibration and air blast will be measured with seismographs located on the West and North side of the subdivision property.  All drilling and blasting operations will be conducted in accordance with:

  • The Village of Waunakee/Town of Westport regulations and permit requirements
  • Bureau of Alcohol, Tobacco and Firearms – 27 CFR 181
  • MSHA 30 CFR Part 56 Safety and Health Standards 
  • MSHA 30 – Subchapter H – Education and Training
  • Wisconsin Department of Safety and Professional Services SPS 307.43 

Questions or concerns regarding the drilling and blasting process should be directed to:

Tom Burke
Account Manager/Blaster
Quick Supply Co.
334 Industrial Drive
Coloma, WI 54930
(608) 778-0385
tburke@quicksupplyco.com 

ATTENTION

QUINCY RIDGE BLASTING
TOWN OF WESTPORT

Wednesday, August 31, 2022

The contractor for the Quincey Ridge Quarry Project, at 6355 Schumacher Road, will be blasting 2-3 times between the hours of 9 a.m. -12 p.m. on Wednesday, August 31, 2022, weather permitting.

There will be three air horn signals sounded one minute prior to each blast followed by one prolonged air horn signal after each blast is deemed all clear.  On average each blast duration is 500 milliseconds, equivalent to half of a second.

Ground vibration and air blast will be measured with seismographs located on the West and North side of the subdivision property.  All drilling and blasting operations will be conducted in accordance with:

  • The Village of Waunakee/Town of Westport regulations and permit requirements
  • Bureau of Alcohol, Tobacco and Firearms – 27 CFR 181
  • MSHA 30 CFR Part 56 Safety and Health Standards 
  • MSHA 30 – Subchapter H – Education and Training
  • Wisconsin Department of Safety and Professional Services SPS 307.43 

Questions or concerns regarding the drilling and blasting process should be directed to:

Tom Burke 
Account Manager/Blaster
Quick Supply Co.
334 Industrial Drive
Coloma, WI 54930
(608) 778-0385
tburke@quicksupplyco.com